Glass fibre plant expansion completed in Ohio

Glass fibre plant expansion completed in Ohio

Phase one of the Johns Manville glass fibre pipe plant expansion in Defiance, Ohio is now complete.

The US expansion added the first of two production lines, improving JM’s ability to meet demand for Micro-Lok HP and Micro-Lok HP Ultra glass fibre pipe insulation, which is used primarily in commercial buildings.  “The JM team has done an outstanding job growing the business to the point where a capacity expansion was necessary” said Jim Swift, Director of Operations in JM’s Insulation Systems business and leader of the expansion project. “The dedication of the entire team made this project possible, with the common goal of supplying our customer with quality pipe insulation and the service they are accustomed to.” 

The project began in March 2019, with an anticipated completion date of early 2020. However, setbacks such as travel limitations due to the Covid-19 pandemic caused a six month delay.

To get it back on track, the JM team in Defiance employed a wearable computer called a HoloLens that rests on the head and acts as a see-through screen, where images may be displayed for the wearer to reference, while still being able to see through the screen into the real world.

The helmet takes high definition footage of the objects in front of the wearer and displays that footage through Microsoft Teams at a remote location.

In JM’s case, the footage was displayed in real-time in Germany, where many of the engineers who worked on the project are based. This technology helped bridge the distance between the engineers in Germany and the team in Defiance, so the expansion could be finished. 