Nigerian container furnace heat-up

Nigerian container furnace heat-up

HORN started the furnace heat-up process at glass packaging supplier Frigoglass' 300 t/d end fired furnace GF2 in Nigeria. Heat-up started on 21 May, with the first glass is expected on 2 June.

The new container glass furnace manufactures glass in green and amber. HORN technicians are present to support the heat-up and establishment of glass making.

The project will be finished by mid of June 2021.

Frigoglass under Manufacturing Director Mr Jagdish Agarwal and the management team provided grateful support in the rapid execution of this project despite the COVID-19 pandemic.

www.hornglass.com

Caption: Frigoglass furnace heat-up under way

Published: 
03/06/2021